Risk Assessment History
Date Prob Score Imp Score Total Score Basis
06/04/2021 3 4 7 Increasing pressure on asset management budgets due to the costs of fire safety remediation and decarbonisation. Forthcoming introduction of the future homes standard.
30/09/2019 2 4 6 Uncertainty over meeting cost of Hackitt Review and additional safety issues associated with timber frame construction etc.
01/07/2019 3 3 6 Additional spending post Grenfell now incorporated into financial plans
29/12/2018 4 3 7 Additional spending post Grenfell now incorporated into financial plans
07/07/2017 3 4 7 Reaction to effects of Grenfell Tower
13/05/2014 2 4 6 Regulatory requirement to report on the return on assets and a drive towards more active asset management in the sector
03/12/2010 2 3 5 Reduced regulatory focus on service quality
11/11/2009 2 3 5 None